  • 不锈钢栏杆规范技术有什么要求
  • 本站编辑:杭州烨群装饰工程有限公司发布日期:2019-05-18 12:27 浏览次数:

1、地面或地面砖铺完7天以后,砂浆强度达到一定程度后方可安装栏杆。

2、用钻机在地面砖上钻孔时,孔洞尺寸应在不锈钢栏杆扣碗扣盖的范围内,且应保护好地面砖,如有地面砖损坏,栏杆施工单位自行承担一切经济损失。

3、将立柱焊接在膨胀螺栓一定要焊接牢固,焊接前要排好立柱的位置。立柱焊接牢固后,及时将不锈钢扣盖扣好,然后即可焊接下部横撑,然后焊接扶手,扶手与立柱焊接后的缝隙不大于0.3mm。横撑全部焊接好后,焊接花管,花管距应相同,以达到美观的效果,立柱、扶手、花管均应两侧焊接,为防止焊缝变形,焊接时应先点焊,后满焊,焊缝应保证均匀一致,美观整齐,扶手焊接后的角度与楼梯的角度应一致,栏杆的弯头应待两侧扶手焊接完毕后,根据实际尺寸另行加工,弯头焊接后应保证角度平滑,缝隙均匀。

4、不锈钢栏杆焊接完毕后,应及时进行焊缝的打磨、抛光,打磨后焊缝的光亮度应与其它地方一致,扶手接头处打磨后应无明显痕迹。

5、不锈钢栏杆立柱、扶手的扣盖应用胶与地面、墙面粘牢,不应活动。

6、施工前应按现场实际情况进行栏板试按,并做样板间,待甲方检查、认可后,方可大面积进行施工。

7、防护栏板安装完后,侧推力不得小于80公斤,手扶栏杆无晃动感。

8、不锈钢栏杆安装完毕后应经公司项目部人员检查、验收、认可后方为合格。


icon3[1].pngicon3[1].png20180118155431172[1].jpg

1, after the ground or ground brick is laid 7 days, the mortar strength reached a certain degree before the railings can be installed.
When drilling the floor brick with a drilling rig, the size of the hole should be within the range of stainless steel railings and buckles, and the floor brick should be protected. If the floor brick is damaged, the railings construction unit shall bear all economic losses on its own.
3, welding the column in the expansion bolt must be welded firmly, before welding to arrange the position of the column. After the column is welded firmly, the stainless steel buckle cover is buckled in time, and then the lower part is welded and then the handrail is welded. The gap between the handrail and the column is not greater than 0.3 mm. After all the horizontal bracing is welded, the tube should be welded at the same distance to achieve a beautiful effect. The columns, handrails, and tubes should be welded on both sides. In order to prevent weld deformation, welding should be done first and then fully welded. The welds should be uniform, beautiful and neat, the angle after the handrail welding should be the same as the angle of the stairs. After the railings are welded on both sides, they should be processed separately according to the actual size. After the welds, the angles should be smooth and the gaps should be uniform.
After welding the stainless steel railings, the weld should be polished and polished in a timely manner. After polishing, the brightness of the weld should be the same as other places. There should be no obvious traces after grinding the handrail joints.
5, stainless steel railings column, armrest of the buckle cover application glue with the ground, wall adhesion, should not be active.
6, construction should be in accordance with the actual situation of the site plate test press, and do the sample room, until the inspection and approval of Party A, before the construction of a large area.
7, after the protective fence plate is installed, the side thrust must not be less than 80 kilograms, and the handrail has no sense of shaking.
After the installation of stainless steel railings, they shall be qualified after inspection, acceptance and approval by the personnel of the company's project department.

 